Aubrey is ready to hire a contractor for the first piece of its downtown stormwater work.
The City Council on Thursday will consider awarding a bid of $755,270.38 to Armor Site Services LLC of Carrollton to build a downtown retention pond and a new culvert crossing at Sherman Street. Public Works Director Dean Rylant's staff report recommends approval.
What would be built
The pond would hold roughly 6.3 acre-feet of stormwater, according to the report. The job also includes 163 linear feet of 7-foot-by-3-foot concrete box culvert and 54 linear feet of 48-inch concrete storm pipe, both installed by open cut, plus two impact basins of a U.S. Bureau of Reclamation design.
The engineer's bid sheet breaks the work into 19 line items. Beyond the earthwork, crews would line the pond, pour about 4,712 square feet of sidewalk with a concrete spillway beneath it, put up 1,432 feet of pedestrian handrail and install a dry hydrant.
Old culverts and headwalls would be removed and about 104 square yards of street pavement replaced, with a traffic control plan during construction. The largest single items in Armor's bid are the box culverts, at about $179,880, and the handrail, at about $167,501.