Eight firms bid on a downtown stormwater pond and Sherman Street culvert; the low offer is $755,270

The City Council votes Thursday on a contract with Carrollton-based Armor Site Services for a pond that would hold about 6.3 acre-feet of runoff, new box culverts under Sherman Street, a sidewalk and handrail.

Marlene Abbott· AI-assisted, edited by Jake Team

November 17, 20262 min read

downtown infrastructure - illustration, Jake Team LLC

Aubrey is ready to hire a contractor for the first piece of its downtown stormwater work.

The City Council on Thursday will consider awarding a bid of $755,270.38 to Armor Site Services LLC of Carrollton to build a downtown retention pond and a new culvert crossing at Sherman Street. Public Works Director Dean Rylant's staff report recommends approval.

What would be built

The pond would hold roughly 6.3 acre-feet of stormwater, according to the report. The job also includes 163 linear feet of 7-foot-by-3-foot concrete box culvert and 54 linear feet of 48-inch concrete storm pipe, both installed by open cut, plus two impact basins of a U.S. Bureau of Reclamation design.

The engineer's bid sheet breaks the work into 19 line items. Beyond the earthwork, crews would line the pond, pour about 4,712 square feet of sidewalk with a concrete spillway beneath it, put up 1,432 feet of pedestrian handrail and install a dry hydrant.

Old culverts and headwalls would be removed and about 104 square yards of street pavement replaced, with a traffic control plan during construction. The largest single items in Armor's bid are the box culverts, at about $179,880, and the handrail, at about $167,501.

How the bids compared

The city advertised the project in the Post Signal on Oct. 9 and Oct. 16 and opened sealed bids Oct. 28. Eight came in. After Armor, the next lowest were Mann Robinson & Son of Aubrey at $877,054.32, Matco of Lake Dallas at $887,402.87 and Quick Set Construction of Corinth at $891,163.70. The highest, from Precision Road Services of Southlake, was $1,914,271.40.

Engineering firm Birkhoff, Hendricks & Carter tabulated the bids and noted small arithmetic and wording discrepancies on several sheets; Armor's corrected total differed from its written figure by $1.04. City staff checked the low bidder's qualifications and references and received no negative responses, the report says.

The report does not say when construction would start or how long it would take.

The council meets at 6 p.m. Thursday, Nov. 19, at 226 Countryside Drive.

Sources

aubreytx.api.civicclerk.com

aubreytx.api.civicclerk.com

Share

Marlene Abbott· AI-assisted, edited by Jake Team

Marlene Abbott writes about community life, schools, public safety, and local events in Aubrey.

Related Stories

More in Texas