Aubrey's planned fire station training center would draw water for drills and landscaping from its own well instead of the public drinking water system, under an engineering contract the City Council considers Thursday.
The agreement with Birkhoff, Hendricks & Carter would cost no more than $198,100 and covers hydrogeologic modeling, permitting, design and construction oversight for the well, according to the staff report for the Nov. 19 meeting. The money comes from the city's 2026 bond, and staff says the funds are available.
The well would sit on city-owned land inside Mustang Special Utility District's service area. It would pull from a shallower aquifer than the public water supply wells in the area, which staff says would conserve drinking water and keep irrigation and training from being restricted in any season.
Plans in the contract call for one well producing about 225 gallons a minute at the future training center site, or at another site if the groundwater study points elsewhere. A proposal from groundwater subconsultant Advanced Groundwater Solutions puts the expected pumping rate at about 200 gallons a minute, for firefighter training and irrigation.
The design work includes a disinfection system, electrical service and a connection to the city's SCADA control system.
The schedule in the staff report:
- Notice to proceed and field surveys: November 2026
- Plan submittals and reviews: February through April 2027
- Final plans and bid advertisement: May 2027
- Construction: June 2027 to an estimated finish in December 2027