Construction is underway on a long-planned widening of US 377 through Argyle, on the highway that links Aubrey and Denton with Fort Worth.
Work began Oct. 13 on the section from Crawford Road and Country Club Road south to FM 1171 in Flower Mound, the Cross Timbers Gazette reported Friday. The two-lane rural highway is being rebuilt as a four-lane divided road, with an overpass at FM 1171. The Texas Department of Transportation expects to finish in 2029, according to the Gazette.
The numbers behind the job
Denton County's September transportation report for Commissioner Precinct 4 lays out the contract. The project went out for bids May 6 and was awarded to Webber LLC, the low bidder at about $111.4 million. Total construction funding listed for the section is about $173 million, drawn from three TxDOT funding categories. The contract allows 876 working days, with 36 months of barricades.
Most utility lines are already clear of the work zone, the report says. Charter/Spectrum and CoServ Electric were still moving lines but were not expected to hold up construction.
The project has been a long time coming. The schematic design was approved in January 2018, environmental clearance followed in March 2019 and land purchases wrapped up in March 2021, the county report shows. The Gazette notes the bid date had already slipped once, from 2022 to 2023, before the project finally let this year.